MakeReady

Seven flows need to come together at the workface to enable value to be created in construction

CPM programmes and Gantt charts don’t deal with all of them - often they only deal with one - prior work.

The MakeReady process in Last Planner® is a simple process to ensure that everything is in place by the time you want to start an activity.

The process was developed when it was recognised that too often work was put into production because the programme said it should be done, yet in reality one or more of the flows was blocked so it could not be completed, or even started.


“if it cannot be done, don’t promise to do it”


The 7 flows required to enable value to be created in construction