Last Planner® benefits

In the UK we have worked on:

  1. Bullettwo Waitrose projects where it created a 20% programme reduction for two different constructors;

  2. Bulleta school project delivered 12 weeks early when the project was running 4 weeks late with 48 to go;

  3. Bulleta city-centre housing project delivered 2 weeks early after it was 7 weeks late with half of the 70 week construction period left to run;

  4. Bulleta Travel Inn & restaurant delivered in 14 weeks instead of 20. 

These are some of the more spectacular results.  It’s used on civil engineering, hotel, health & commercial projects too.  Few of these projects used 100% of Last Planner. 

In South Africa we are working with a civils team working through the uncertainty of the rainy season on enabling works for an open-cast pit.

Last Planner offers a wide range of benefits – many are summarised in Last_Planner_5_crucial_conversations.pdf   

To learn more of the benefits first hand join the Study Tour to N California

when is the right time to
begin lean on a project?